| Completion of Police Operations Building Project (Phase 2) | Spring 2026 (Anticipated) |
| Grand Opening of Police Operations Building (Phase 1) | December 2025 (Anticipated) |
| Start of Construction | February 2024 |
| Groundbreaking | January 2024 |
| Council Award of Construction Contract | November 2023 |
| Bid Closing for General Contractor | October 2023 |
| Council Approval of Final Project Plans, Specs and Estimates | July 2023 |
CEQA Clearance (Mitigated Negative Declaration) | August 2021 |
| Schematic Design Approved | May 2021 |
| Start of Design | May 2020 |